Project List

MTP ID Project Improvement Type Existing Number of Lanes Proposed Number of Lanes Extent To Extent From Estimated Cost Staff Comments
449 Red Mill Rd (realignment) New Location 0 2 Red Mill Rd Teknika Pkwy $2,266,000.00
61 Old Oxford Connector New Location 0 2 Thompson Rd Dearborn Dr $4,092,000.00 one-fifth is already built
334 Cheek Rd Modernization 2 2 Junction Rd US 70 $7,071,000.00
404 Lynn Rd Modernization 2 2 NC 98 (Holloway St) Gibson Rd $5,020,000.00
407 Lynn Rd/Pleasant Dr Connector New Location 0 2 Pleasant Dr Lynn Rd $3,651,000.00 Built as part of East End Connector
331 Carr Rd Extension New Location 0 2 US 70/Carr Rd Angier Av $5,452,000.00
244 Angier/Glover Connector New Location 0 2 Glover Rd Ellis Rd $8,625,000.00
328 Carpenter Pond Rd Extension Modernization 2 2 Leesville Rd Carpenter Pond Rd $3,627,000.00
358 Ellis-Glover Connector New Location 0 2 Glover Rd Ellis Rd $8,058,000.00
343 Crown Pkwy/Roche Dr New Location 0 2 T.W. Alexander Dr Page Rd $11,041,000.00 2/5 built already
464 Smallwood Dr Extension New Location 0 2 Page Rd Crown Pkwy/Roche Dr $3,022,000.00 Part of this road already built? If so, adjust!
10 Chin Page Rd Extension Add Access 0 2 Airport Rd Page Rd
440 New Hope Commons Dr Extension New Location 0 2 New Hope Commons Dr Eastowne Dr $4,588,000.00
346 Danziger Dr Extension New Location 0 2 E Lakewood Dr Mt Moriah Rd $5,127,000.00
230 Southwest Durham Dr New Location 0 2 I-40 NC 54 $12,402,000.00 10% built, but no 2-lane div cost avail
Page 10 of 16