Bike-Ped project in Carrboro. This is the parent project for the Morgan Creek Greenway in Carrboro. The project was split into sections A and B, and B was cancelled pending future funding. All sections are west of Smith Level Road.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Totals: | $0 | $0 | $0 | $0 |
Bike-Ped project in Carrboro. This is the parent project for the Morgan Creek Greenway in Carrboro. The project was split into sections A and B, and B was cancelled pending future funding. All sections are west of Smith Level Road.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Totals: | $0 | $0 | $0 | $0 |
Bike-Ped project in Chapel Hill. This segment of the Morgan Creek Greenway would connect the existing path at the trailhead to the soon-to-be-constructed Carrboro portion at Smith Level Road. The existing greenway is highly used and extending it to the west to Carrboro and beyond has long been a priority for both Towns.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Totals: | $0 | $0 | $0 | $0 |
Bike-Ped project in Chapel Hill. This segment of the Morgan Creek Greenway would connect the existing path at the trailhead to the soon-to-be-constructed Carrboro portion at Smith Level Road. The existing greenway is highly used and extending it to the west to Carrboro and beyond has long been a priority for both Towns.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Totals: | $0 | $0 | $0 | $0 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. As part of TIP Amendment #6, Phase 2 was deleted. Planning, design, right of way, and construction for this project are by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |
Bike-Ped project in Chapel Hill. This segment of the Morgan Creek Greenway would connect the existing path at the trailhead to the soon-to-be-constructed Carrboro portion at Smith Level Road. The existing greenway is highly used and extending it to the west to Carrboro and beyond has long been a priority for both Towns.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. As part of TIP Amendment #6, Phase 2 was deleted. Planning, design, right of way, and construction for this project are by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. This project is for Phase 1 and Phase 2 of the western section of Morgan Creek Greenway. Phase 1 construction costs are $372,000. Phase 2 construction costs are $912,000. Each phase is shown separately in the project schedule. Planning, design, right of way, and construction for this project are in progress by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. This project is for Phase 1 and Phase 2 of the western section of Morgan Creek Greenway. Phase 1 construction costs are $372,000. Phase 2 construction costs are $912,000. Each phase is shown separately in the project schedule. Planning, design, right of way, and construction for this project are in progress by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. This project is for Phase 1 and Phase 2 of the western section of Morgan Creek Greenway. Phase 1 construction costs are $372,000. Phase 2 construction costs are $912,000. Each phase is shown separately in the project schedule. Planning, design, right of way, and construction for this project are in progress by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. This project is for Phase 1 and Phase 2 of the western section of Morgan Creek Greenway. Phase 1 construction costs are $372,000. Phase 2 construction costs are $912,000. Each phase is shown separately in the project schedule. Planning, design, right of way, and construction for this project are in progress by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,655,200 | $0 | $412,800 | $2,068,000 | ||
Totals: | $1,655,200 | $0 | $412,800 | $2,068,000 |