Upgrade I-85/NC-86 interchange in Hillsborough.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2027 | $1,710,000 | $190,000 | $0 | $1,900,000 |
NHP | Utilities | 2027 | $2,070,000 | $230,000 | $0 | $2,300,000 |
NHP | Construction | 2029 | $6,967,000 | $0 | $0 | $6,967,000 |
NHP | Construction | Future Unfunded | $13,933,000 | $0 | $0 | $13,933,000 |
Totals: | $24,680,000 | $420,000 | $0 | $25,100,000 |
Upgrade I-85/NC-86 interchange in Hillsborough.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2027 | $1,710,000 | $190,000 | $0 | $1,900,000 |
NHP | Utilities | 2027 | $2,070,000 | $230,000 | $0 | $2,300,000 |
NHP | Construction | 2029 | $6,967,000 | $0 | $0 | $6,967,000 |
NHP | Construction | Future Unfunded | $13,933,000 | $0 | $0 | $13,933,000 |
Totals: | $24,680,000 | $420,000 | $0 | $25,100,000 |
Upgrade I-85/NC-86 interchange in Hillsborough.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2024 | $1,710,000 | $190,000 | $0 | $1,900,000 |
NHP | Utilities | 2024 | $2,070,000 | $230,000 | $0 | $2,300,000 |
NHP | Construction | 2026 | $9,405,000 | $1,045,000 | $0 | $10,450,000 |
NHP | Construction | 2027 | $9,405,000 | $1,045,000 | $0 | $10,450,000 |
Totals: | $22,590,000 | $2,510,000 | $0 | $25,100,000 |
Upgrade I-85/NC-86 interchange in Hillsborough.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2024 | $1,710,000 | $190,000 | $0 | $1,900,000 |
NHP | Utilities | 2024 | $2,070,000 | $230,000 | $0 | $2,300,000 |
NHP | Construction | 2026 | $9,405,000 | $1,045,000 | $0 | $10,450,000 |
NHP | Construction | 2027 | $9,405,000 | $1,045,000 | $0 | $10,450,000 |
Totals: | $22,590,000 | $2,510,000 | $0 | $25,100,000 |
Upgrade I-85/NC-86 interchange in Hillsborough.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2024 | $4,410,000 | $490,000 | $0 | $4,900,000 |
NHP | Utilities | 2024 | $529,000 | $59,000 | $0 | $588,000 |
NHP | Construction | 2026 | $9,900,000 | $1,100,000 | $0 | $11,000,000 |
Totals: | $14,839,000 | $1,649,000 | $0 | $16,488,000 |