Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 5.0 miles.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
T | Right of Way | 2027 | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | 2027 | $0 | $325,000 | $0 | $325,000 |
T | Right of Way | 2028 | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | 2028 | $0 | $325,000 | $0 | $325,000 |
T | Right of Way | 2029 | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | 2029 | $0 | $325,000 | $0 | $325,000 |
T | Right of Way | Future Unfunded | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | Future Unfunded | $0 | $325,000 | $0 | $325,000 |
T | Construction | Future Unfunded | $0 | $32,500,000 | $0 | $32,500,000 |
Totals: | $0 | $62,700,000 | $0 | $62,700,000 |
Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 5.0 miles.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
T | Right of Way | 2027 | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | 2027 | $0 | $325,000 | $0 | $325,000 |
T | Right of Way | 2028 | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | 2028 | $0 | $325,000 | $0 | $325,000 |
T | Right of Way | 2029 | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | 2029 | $0 | $325,000 | $0 | $325,000 |
T | Right of Way | Future Unfunded | $0 | $7,225,000 | $0 | $7,225,000 |
T | Utilities | Future Unfunded | $0 | $325,000 | $0 | $325,000 |
T | Construction | Future Unfunded | $0 | $32,500,000 | $0 | $32,500,000 |
Totals: | $0 | $62,700,000 | $0 | $62,700,000 |
Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 5.0 miles.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $0 | $31,287,000 | $0 | $31,287,000 | ||
T | Right of Way | 2024 | $0 | $14,450,000 | $0 | $14,450,000 |
T | Construction | 2027 | $0 | $8,125,000 | $0 | $8,125,000 |
T | Construction | 2028 | $0 | $8,125,000 | $0 | $8,125,000 |
T | Construction | Future Unfunded | $0 | $8,125,000 | $0 | $8,125,000 |
Totals: | $0 | $70,112,000 | $0 | $70,112,000 |
Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 5.0 miles.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $0 | $31,287,000 | $0 | $31,287,000 | ||
T | Right of Way | 2024 | $0 | $14,450,000 | $0 | $14,450,000 |
T | Construction | 2027 | $0 | $8,125,000 | $0 | $8,125,000 |
T | Construction | 2028 | $0 | $8,125,000 | $0 | $8,125,000 |
T | Construction | Future Unfunded | $0 | $8,125,000 | $0 | $8,125,000 |
Totals: | $0 | $70,112,000 | $0 | $70,112,000 |
Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 1.6 miles. Total project cost for the entire project is $136,124,000. Break A of this project is US 70 (Miami Blvd) from Lynn Road to SR 1959 (S Miami Blvd) / SR 1811 (Sherron Rd). Project costs for only Break A are shown in the table below. Planning and design for this project are in progress.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $0 | $54,187,000 | $0 | $54,187,000 | ||
T | Construction | 2024 | $0 | $13,538,000 | $0 | $13,538,000 |
T | Construction | 2025 | $0 | $13,538,000 | $0 | $13,538,000 |
T | Construction | 2026 | $0 | $13,537,000 | $0 | $13,537,000 |
Totals: | $0 | $94,800,000 | $0 | $94,800,000 |
Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 1.6 miles. Total project cost for the entire project is $136,124,000. Break A of this project is US 70 (Miami Blvd) from Lynn Road to SR 1959 (S Miami Blvd) / SR 1811 (Sherron Rd). Project costs for only Break A are shown in the table below. Planning and design for this project are in progress.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $0 | $54,187,000 | $0 | $54,187,000 | ||
T | Construction | 2024 | $0 | $13,538,000 | $0 | $13,538,000 |
T | Construction | 2025 | $0 | $13,538,000 | $0 | $13,538,000 |
T | Construction | 2026 | $0 | $13,537,000 | $0 | $13,537,000 |
Totals: | $0 | $94,800,000 | $0 | $94,800,000 |
Full U-5720 project information is Lynn Road in Durham to west of Alexander Drive in Raleigh. Upgrade to controlled-access facility and convert at-grade intersection with SR 1811/ SR 1959 to interchange. Total project length is 1.6 miles. Total project cost for the entire project is $136,124,000. Break A of this project is US 70 (Miami Blvd) from Lynn Road to SR 1959 (S Miami Blvd) / SR 1811 (Sherron Rd). Project costs for only Break A are shown in the table below. Planning and design for this project are in progress.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $0 | $32,315,000 | $0 | $32,315,000 | ||
T | Construction | 2024 | $0 | $26,235,000 | $0 | $26,235,000 |
T | Construction | 2025 | $0 | $26,235,000 | $0 | $26,235,000 |
T | Construction | Future Unfunded | $0 | $26,235,000 | $0 | $26,235,000 |
Totals: | $0 | $111,020,000 | $0 | $111,020,000 |