The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. Break F of the project is the I-40/NC 54 interchange improvements, which include grade separations at Falconbridge and Farrington roads. Previous breaks D and E were incorporated into break F in P4.0.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2029 | $301,000 | $0 | $75,000 | $376,000 |
NHP | Utilities | 2029 | $1,295,000 | $0 | $324,000 | $1,619,000 |
NHP | Construction | Future Unfunded | $1,438,000 | $0 | $360,000 | $1,798,000 |
Totals: | $3,034,000 | $0 | $759,000 | $3,793,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. Break F of the project is the I-40/NC 54 interchange improvements, which include grade separations at Falconbridge and Farrington roads. Previous breaks D and E were incorporated into break F in P4.0.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2029 | $301,000 | $0 | $75,000 | $376,000 |
NHP | Utilities | 2029 | $1,295,000 | $0 | $324,000 | $1,619,000 |
NHP | Construction | Future Unfunded | $1,438,000 | $0 | $360,000 | $1,798,000 |
Totals: | $3,034,000 | $0 | $759,000 | $3,793,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. Break F of the project is the I-40/NC 54 interchange improvements, which include grade separations at Falconbridge and Farrington roads. Previous breaks D and E were incorporated into break F in P4.0.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2025 | $37,413,000 | $0 | $0 | $37,413,000 |
NHP | Utilities | 2025 | $800,000 | $0 | $0 | $800,000 |
NHP | Right of Way | 2026 | $37,413,000 | $0 | $0 | $37,413,000 |
NHP | Right of Way | 2027 | $37,412,000 | $0 | $0 | $37,412,000 |
NHP | Construction | 2029 | $9,825,000 | $0 | $0 | $9,825,000 |
NHP | Construction | Future Unfunded | $29,475,000 | $0 | $0 | $29,475,000 |
Totals: | $152,338,000 | $0 | $0 | $152,338,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. Break F of the project is the I-40/NC 54 interchange improvements, which include grade separations at Falconbridge and Farrington roads. Previous breaks D and E were incorporated into break F in P4.0.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | 2025 | $16,200,000 | $1,800,000 | $0 | $18,000,000 |
NHP | Utilities | 2025 | $720,000 | $80,000 | $0 | $800,000 |
NHP | Right of Way | 2026 | $16,200,000 | $1,800,000 | $0 | $18,000,000 |
NHP | Right of Way | 2027 | $16,200,000 | $1,800,000 | $0 | $18,000,000 |
NHP | Construction | Future Unfunded | $26,527,500 | $2,947,500 | $0 | $29,475,000 |
Totals: | $75,847,500 | $8,427,500 | $0 | $84,275,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. The total project cost for the entire project is $228,859,000. Break F of the project is the I-40/NC 54 interchange improvements. Previous breaks D and E were incorporated into break F in P4.0. ***Cost estimates for improvements to interchange may change during planning and design.*** Project costs for Break F are shown in the table below. Planning and design for this project are in progress. Breaks A through F are on expanded NHS. Coordinate this project with TE-5205 (Previous TIP # U-5324.) and R-5821.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $0 | $0 | $0 | $0 | ||
NHP | Right of Way | Future Unfunded | $48,600,000 | $5,400,000 | $0 | $54,000,000 |
NHP | Utilities | Future Unfunded | $720,000 | $80,000 | $0 | $800,000 |
NHP | Construction | Future Unfunded | $35,370,000 | $3,930,000 | $0 | $39,300,000 |
Totals: | $84,690,000 | $9,410,000 | $0 | $94,100,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. The total project cost for the entire project is $228,859,000. Break F of the project is the I-40/NC 54 interchange improvements. Previous breaks D and E were incorporated into break F in P4.0. ***Cost estimates for improvements to interchange may change during planning and design.*** Project costs for Break F are shown in the table below. Planning and design for this project are in progress. Breaks A through F are on expanded NHS. Coordinate this project with TE-5205 (Previous TIP # U-5324.) and R-5821.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
NHP | Right of Way | Future Unfunded | $48,600,000 | $5,400,000 | $0 | $54,000,000 |
NHP | Utilities | Future Unfunded | $720,000 | $80,000 | $0 | $800,000 |
NHP | Construction | Future Unfunded | $35,370,000 | $3,930,000 | $0 | $39,300,000 |
Totals: | $84,690,000 | $9,410,000 | $0 | $94,100,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. The total project cost for the entire project is $228,859,000. Break F of the project is the I-40/NC 54 interchange improvements. ***Cost estimates for improvements to interchange may change during planning and design.*** Project costs for Break F are shown in the table below. Planning and design for this project are in progress. Breaks A through F are on expanded NHS. Coordinate this project with TE-5205. (Previous TIP # U-5324.)
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $385,200 | $42,800 | $0 | $428,000 | ||
NHP | Construction | 2025 | $900,000 | $100,000 | $0 | $1,000,000 |
Totals: | $1,285,200 | $142,800 | $0 | $1,428,000 |
The full project #U-5774 is NC 54 from US 15/501 in Chapel Hill to NC 55 in Durham, upgrade roadway corridor. Total project length for all sections is 9.2 miles. The total project cost for the entire project is $228,859,000. Break F of the project is the I-40/NC 54 interchange improvements. ***Cost estimates for improvements to interchange may change during planning and design.*** Project costs for Break F are shown in the table below. Planning and design for this project are in progress. Breaks A through F are on expanded NHS. Coordinate this project with TE-5205. (Previous TIP # U-5324.)
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $385,200 | $42,800 | $0 | $428,000 | ||
NHP | Construction | 2024 | $900,000 | $100,000 | $0 | $1,000,000 |
Totals: | $1,285,200 | $142,800 | $0 | $1,428,000 |