Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $737,800 | $0 | $184,200 | $922,000 | ||
Totals: | $737,800 | $0 | $184,200 | $922,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $737,800 | $0 | $184,200 | $922,000 | ||
Totals: | $737,800 | $0 | $184,200 | $922,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $533,000 | $0 | $133,000 | $666,000 | ||
Totals: | $533,000 | $0 | $133,000 | $666,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $612,600 | $0 | $153,400 | $766,000 | ||
Totals: | $612,600 | $0 | $153,400 | $766,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $612,600 | $0 | $153,400 | $766,000 | ||
Totals: | $612,600 | $0 | $153,400 | $766,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $612,600 | $0 | $153,400 | $766,000 | ||
Totals: | $612,600 | $0 | $153,400 | $766,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $680,200 | $0 | $170,050 | $850,250 | ||
Totals: | $680,200 | $0 | $170,050 | $850,250 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $370,600 | $0 | $91,400 | $462,000 | ||
Totals: | $370,600 | $0 | $91,400 | $462,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $336,600 | $0 | $83,400 | $420,000 | ||
Totals: | $336,600 | $0 | $83,400 | $420,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $370,600 | $0 | $91,400 | $462,000 | ||
Totals: | $370,600 | $0 | $91,400 | $462,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $336,400 | $0 | $83,600 | $420,000 | ||
Totals: | $336,400 | $0 | $83,600 | $420,000 |
Construct a 100 foot bridge and 650 foot paved trail in Carrboro to fill gap between the Upper Bolin Trail and Twin Creeks Greenway and implement program to support non-vehicle trips to Morris Grove Elementary School. Planning, design, right of way, and construction by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $257,000 | $0 | $63,000 | $320,000 | ||
Totals: | $257,000 | $0 | $63,000 | $320,000 |