Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. As part of TIP Amendment #6, Phase 2 was deleted. Planning, design, right of way, and construction for this project are by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,254,000 | $0 | $313,500 | $1,567,500 | ||
Totals: | $1,254,000 | $0 | $313,500 | $1,567,500 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. As part of TIP Amendment #6, Phase 2 was deleted. Planning, design, right of way, and construction for this project are by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,254,000 | $0 | $313,500 | $1,567,500 | ||
Totals: | $1,254,000 | $0 | $313,500 | $1,567,500 |
Western section, SR 1919 (Smith Level Road) to University Lake in Carrboro. Construct greenway and connections. As part of TIP Amendment #6, Phase 2 was deleted. Planning, design, right of way, and construction for this project are by the Town of Carrboro.
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $1,254,000 | $0 | $313,500 | $1,567,500 | ||
Totals: | $1,254,000 | $0 | $313,500 | $1,567,500 |
Funding Source | Phase | Year | Federal | State | Local | Total |
---|---|---|---|---|---|---|
Prior Years | $298,000 | $0 | $74,000 | $372,000 | ||
Totals: | $298,000 | $0 | $74,000 | $372,000 |