MTP ID Project Improvement Type Existing Number of Lanes Proposed Number of Lanes Extent To Extent From Estimated Cost Staff Comments
307 Avondale Dr (NC 55) Widening 2 4 I-85 E Geer St $7,551,000.00 Used 100% for ROW
310 Big Woods Rd Modernization 2 2 Gallup Rd Jack Bennett Rd $10,830,000.00
313 Brier Creek Pkwy Extension Widening 2 4 Andrew's Chapel Rd Leesville Rd $4,033,000.00
316 Brier Creek Pkwy Extension New Location 0 4 Andrew's Chapel Rd T.W. Alexander Dr $3,990,000.00 Private $. under const.
322 Broad St Widening 2 3 Stadium Dr W Carver St $1,781,000.00
325 Carpenter Pond Rd Widening 2 4 Leesville Rd Olive Branch Rd $2,662,000.00
328 Carpenter Pond Rd Extension Modernization 2 2 Leesville Rd Carpenter Pond Rd $3,627,000.00
331 Carr Rd Extension New Location 0 2 US 70/Carr Rd Angier Av $5,452,000.00
334 Cheek Rd Modernization 2 2 Junction Rd US 70 $7,071,000.00
337 Cole Mill Rd Widening 2 4 Rose of Sharon Rd Sparger Rd $10,011,000.00
340 Cole Mill Rd Modernization 4 4 I-85 Rose of Sharon Rd $7,906,000.00
343 Crown Pkwy/Roche Dr New Location 0 2 T.W. Alexander Dr Page Rd $11,041,000.00 2/5 built already
346 Danziger Dr Extension New Location 0 2 E Lakewood Dr Mt Moriah Rd $5,127,000.00
349 Durham-Chapel Hill Blvd (US 15-501 Bus) Modernization 4 4 University Dr US 15-501 Bypass $12,847,000.00
35 Homestead Rd Modernization 2 2 NC 86 Rogers Rd $6,855,000.00 by mileage from SPOT 4.0; op imp.