Project Description

Full U-5304 project is NC 86 (S Columbia St) to I-40 in Chapel Hill. Upgrade corridor. Total project length is 6.0 miles. Total project cost for the entire project is $131,266,000. Break A is for improvements for the NC 86 (S Columbia St) interchange in Chapel Hill. Project costs for only Break A are shown in the table below. Planning and design are in progress.

Project Information

TIP #
U-5304A
Project Status
Active
Mode
Highway
WBS #
N/A
Federal Project #
N/A
MUNIS Grant #
N/A
Date Awarded
N/A
Program(s)
N/A
Project Type(s)
Intersection Improvements, Roadway Capacity, Urban
Project Length
N/A
Regions
Region D
Divisions
Division 7
Counties
Orange County
Municipalities
Town of Chapel Hill
Agencies
NCDOT

Amendment Information

TIP Amendment #
TIP Amendment Adopted Date
STIP Amendment Date
Amendment Description

SPOT Information

SPOT ID
H149001-A
SPOT Process #
4.0
Statewide Mobility (Raw)
66.65
Regional Impact (Raw)
73.85
Division Needs (Raw)
32.94
Local Input Points (Regional Impact)
N/A
Local Input Points (Division Needs)
N/A

Project Files

Interactive Project Map http://arcg.is/1mblnNy

Project Schedule

Funding Source Phase Year Federal State Local Total Obligated Local Responsibility
T Right of Way 2026 $0 $5,000,000 $0 $5,000,000 $0
T Utilities 2026 $0 $520,000 $0 $520,000 $0
T Right of Way 2027 $0 $5,000,000 $0 $5,000,000 $0
T Utilities 2027 $0 $520,000 $0 $520,000 $0
T Construction Future Unfunded $0 $16,500,000 $0 $16,500,000 $0
Totals: $0 $27,540,000 $0 $27,540,000 $0