Project Description

The NC 54-Falconbridge construction project aims to address critical transit access and transit operation safety concerns along NC 54 in the Falconbridge area in southwestern Durham County, thereby increasing transit ridership and reducing emissions. The project is located within City of Durham city limits from Farrington Road to Huntingridge Road. The project will provide safe pedestrian connections for transit users to existing and planned signalized crossings in this corridor, given the high speeds and traffic volumes on NC 54. The project includes construction of bus stop landing pads, shelters, benches, bus pullouts and tapers, sidewalk, curb and gutter, curb ramps, crosswalks, pedestrian median refuge islands, appropriate safety signage, pedestrian signal heads and complimentary traffic signal modifications, and other supporting roadway modifications.

Project Information

TIP #
TL-0027
Project Status
Active
Mode
Public Transportation
WBS #
N/A
Federal Project #
N/A
MUNIS Grant #
N/A
Date Awarded
N/A
Program(s)
N/A
Project Type(s)
N/A
Project Length
N/A
Regions
N/A
Divisions
N/A
Counties
Durham County
Municipalities
N/A
Agencies
GoTriangle

Amendment Information

TIP Amendment #
14
TIP Amendment Adopted Date
4/12/2023
STIP Amendment Date
Amendment Description
Original STIP# TL-0025 was duplicated and exists for another jurisdiction. Project was never added to STIP due to discrepancy. Update with new STIP# and add project to STIP.

SPOT Information

SPOT ID
N/A
SPOT Process #
N/A
Statewide Mobility (Raw)
N/A
Regional Impact (Raw)
N/A
Division Needs (Raw)
N/A
Local Input Points (Regional Impact)
N/A
Local Input Points (Division Needs)
N/A

Project Files

Project Schedule

Funding Source Phase Year Federal State Local Total Obligated Local Responsibility
Prior Years $903,320 $0 $232,580 $1,135,900 $0
Totals: $903,320 $0 $232,580 $1,135,900 $0