Project Description
Upgrade US 70 from west of TW Alexander Drive (SR 3067) to I-540 in Raleigh to improve capacity, safety, and traffic operations including interchanges at various locations.
Project Information
TIP #
U-5518
Project Status
Active
Mode
Highway
WBS #
N/A
Federal Project #
N/A
MUNIS Grant #
N/A
Date Awarded
4/4/2019
Program(s)
N/A
Project Type(s)
Additional Lanes , Highway Program
Project Length
2.7 miles
Regions
Region C
Divisions
Division 5
Counties
Durham County
Municipalities
City of Durham
Agencies
NCDOT
Amendment Information
TIP Amendment #
3
TIP Amendment Adopted Date
1/13/2021
STIP Amendment Date
4/4/2019
Amendment Description
TO ASSIST IN BALANCING FUNDS, DELAY RIGHT-OFWAY
AND CONSTRUCTION FROM FY 22 TO FY 25.
SPOT Information
SPOT ID
H128081
SPOT Process #
4.0
Statewide Mobility (Raw)
75.3
Regional Impact (Raw)
48.66
Division Needs (Raw)
35.99
Local Input Points (Regional Impact)
N/A
Local Input Points (Division Needs)
N/A
Project Files
Project Schedule
Funding Source | Phase | Year | Federal | State | Local | Total | Obligated | Local Responsibility |
---|---|---|---|---|---|---|---|---|
NHP | Right of Way | 2025 | $2,604,000 | $18,500,000 | $0 | $21,104,000 | $0 | |
NHP | GARVEE ROW | 2025 | $9,524,000 | $0 | $0 | $9,524,000 | $0 | |
NHP | Utilities | 2025 | $12,720,000 | $0 | $0 | $12,720,000 | $0 | |
NHP | Construction | 2025 | $2,525,000 | $9,500,000 | $0 | $12,025,000 | $0 | |
NHP | Construction Garvee | 2025 | $9,781,000 | $0 | $0 | $9,781,000 | $0 | |
NHP | Right of Way | 2026 | $2,604,000 | $18,500,000 | $0 | $21,104,000 | $0 | |
NHP | GARVEE ROW | 2026 | $9,524,000 | $0 | $0 | $9,524,000 | $0 | |
NHP | Construction | 2026 | $2,525,000 | $9,500,000 | $0 | $12,025,000 | $0 | |
NHP | Construction Garvee | 2026 | $9,781,000 | $0 | $0 | $9,781,000 | $0 | |
NHP | GARVEE ROW | 2027 | $9,524,000 | $0 | $0 | $9,524,000 | $0 | |
NHP | Construction | 2027 | $2,525,000 | $9,500,000 | $0 | $12,025,000 | $0 | |
NHP | Construction Garvee | 2027 | $9,781,000 | $0 | $0 | $9,781,000 | $0 | |
NHP | GARVEE ROW | 2028 | $9,524,000 | $0 | $0 | $9,524,000 | $0 | |
NHP | Construction | 2028 | $2,525,000 | $9,500,000 | $0 | $12,025,000 | $0 | |
NHP | Construction Garvee | 2028 | $9,781,000 | $0 | $0 | $9,781,000 | $0 | |
NHP | GARVEE ROW | 2029 | $9,524,000 | $0 | $0 | $9,524,000 | $0 | |
NHP | Construction Garvee | 2029 | $9,781,000 | $0 | $0 | $9,781,000 | $0 | |
NHP | GARVEE ROW | Future Unfunded | $95,237,000 | $0 | $0 | $95,237,000 | $0 | |
NHP | Construction Garvee | Future Unfunded | $97,813,000 | $0 | $0 | $97,813,000 | $0 | |
Totals: | $317,603,000 | $75,000,000 | $0 | $392,603,000 | $0 |